Ansar expects to connect up to 20 villages by late 2012 using internal resources, which will provide over a year of actual operating results.
By mid 2013, Ansar would like to have a $1 million debt facility to fund one additional generating facility, supplying electricity to an additional 20 to 40 villages.
By late 2014, after completion of the first expansion, Ansar would like to have a $10 million debt facility, to implement 10 generating facilities, supplying electricity to an additional ~200 to 400 villages (0.2% of market).