Sustainable Energy Projects

Sustainable Energy Projects

Solar Program Overview

Solar Program Sites

About Solar Energy

How PV Solar Works

Large PV Solar Plants

Project Construction

Why Solar Energy in Mass: Green Communites Act

Economics & Environment: Permitting

News/Community Reaction

Development Relationships

Permitting

Large scale PV projects can typically be permitted within 6 months compared to multi-year permitting periods for any other utility scale fossil or renewable power projects.

Permitting Milestones Completed by:
Site Engineering Design and Electrical Interconnection Study Complete Week 0
MEPA - Environmental Notification Forms (If applicable)
 - Prepare and File the ENF Week 4
 - Agency Review & Approval Week 13
DEP - Post-Closure Use Permit Application (Landfill site)
 - Prepare and File the Application Week 4
 - Agency Review & Approval (2-4 Months) Week 15-20
EPA - Storm Water Construction Permit, Notice-of-intent Week 15
Municipal Permits and Approvals (e.g. Zoning, Special Permits)
 - Identify Requirements Week 2
 - Prepare and File Applications Week 6
 - Municipal Review and Approval (Timeframe Can Vary Considerably) Week 15-20+
Site Lease with Host Community Executed (Attaches to DEP Post-Closure Use Permit) Week 15-20+