| Site Engineering Design and Electrical Interconnection Study Complete |
Week 0 |
| MEPA - Environmental Notification Forms (If applicable) |
|
| - Prepare and File the ENF |
Week 4 |
| - Agency Review & Approval |
Week 13 |
| DEP - Post-Closure Use Permit Application (Landfill site) |
|
| - Prepare and File the Application |
Week 4 |
| - Agency Review & Approval (2-4 Months) |
Week 15-20 |
| EPA - Storm Water Construction Permit, Notice-of-intent |
Week 15 |
| Municipal Permits and Approvals (e.g. Zoning, Special Permits) |
|
| - Identify Requirements |
Week 2 |
| - Prepare and File Applications |
Week 6 |
| - Municipal Review and Approval (Timeframe Can Vary Considerably) |
Week 15-20+ |
| Site Lease with Host Community Executed (Attaches to DEP Post-Closure Use Permit) |
Week 15-20+ |
| |
|